Section 22-74 Payment of differential cost for water and sewer lines.


When a property owner is extending a water or sewer line to serve the owner’s property, the city may require the property owner to increase the size of the water or sewer line in order to provide adequate service to other areas.  The city, in such cases, shall pay the property owner for the extra cost incurred in building the larger water or sewer line.  The city manager may authorize such projects involving city payments of up to twenty-five thousand dollars ($25,000.00). Projects requiring city payments exceeding twenty-five thousand dollars ($25,000.00) must be authorized by the city council.

(Code 1964, § 14.390; Ord. No. 18879, § 1, 2-6-06; Ord. No. 20207, § 1, 3-2-09; Ord. No. 20880, § 2, 2-21-11 )

     Charter reference(s)--Similar provisions, § 75.


(Ord. 20880, Amended, 02/21/2011, Prior Text; Ord. 20207, Amended, 03/02/2009, Prior Text; Ord. 18879, Amended, 02/06/2006, Prior Text)