Section 22-76 Design-build contracts.


    (a)     If the council determines that a public improvement should be constructed using a design-build contract, the procedure set forth in section 22-71 shall be modified as set forth in this section.

    (b)     Following the public hearing, the council shall authorize the city manager to proceed with selection of a design-build contractor.

    (c)    The city manager may award the design-build contract to the contractor that, in the opinion of the city manager, has submitted the best proposal based on the following factors:

    (1)    Proposed cost;

    (2)    City’s previous experience with the contractor;

    (3)    Reputation of the contractor;

    (4)    Technical capability of the contractor; and

    (5)    Any other factors deemed relevant by the manager.


(Code 1964, §§ 14.350, 14.450; Ord. No. 20880, § 2, 2-21-11 )

     Charter reference(s)--Similar provisions, §§ 72, 78.


(Ord. 20880, Amended, 02/21/2011, Prior Text)