Chapter 25 SUBDIVISIONS*
Section 25-47.03 Calculation of impact fee.
(a) The local street portion of costs or the actual construction
costs per foot, whichever is
applicable, shall be determined by the director of public works prior to final plat approval.
(b) The number of abutting feet shall then be calculated
and multiplied by the local street
portion of costs, or the actual construction costs per foot to determine the total amount of the
impact fee.
(c) If a special assessment has been levied against the property
a proportionate amount shall be
subtracted from the impact fee.
(d) The director of public works shall certify the amount
of the impact fee to the director of
planning and development for collection.
(Ord. No. 10833, § 5, 12-16-85)