Section 101-177 Ord. 16410; Change Order No. 1 to Contract w/J.C. Industries, Inc. RE: Construction of H-4 Trunk Sewer


Ordinance No.            16410              Council Bill No.           B 98-00            

AN ORDINANCE

authorizing the City Manager to execute Change Order No. One to the contract with J.C. Industries, Inc. for construction of the H-4 Trunk Sewer; setting forth the nature and amount of change; accepting and approving the work; approving the report of the Director of Public Works; and fixing the time when this ordinance shall become effective.

    WHEREAS, construction of the H-4 Trunk Sewer was authorized by Ordinance No. 015809 passed on November 16, 1998; and

    WHEREAS, this public improvement has been completed by J.C. Industries, Inc. pursuant to a contract confirmed by Ordinance No. 015862 passed on January 4, 1999.

    NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBIA, MISSOURI, AS FOLLOWS:

    SECTION 1.  The City Manager is hereby authorized and directed to execute Change Order No. One to the contract with J.C. Industries, Inc. for the construction of the H-4 Trunk Sewer.

    SECTION 2.  The nature and amount of the change is set forth in Exhibit "A" attached hereto and made a part hereof as fully as if set forth herein verbatim.

    SECTION 3.  The construction of the H-4 Trunk Sewer is hereby accepted and approved.

    SECTION 4.  The report of the Director of the Public Works Department, who was charged with the responsibility of personally inspecting the work as it progressed to see that the work was done in accordance with the estimate, plans, specifications and contract, the ordinance governing the same and the Charter of the City is hereby approved and accepted.

    SECTION 5.  This ordinance shall be in full force and effect from and after its passage.

    PASSED this 17th day of April, 2000.