Series 102 2001 ORDINANCES/RESOLUTIONS
Section 102-071 Ord. 16777; Contract w/C.L. Richardson Construction Company RE: Street Improvements at Intersection of Keene Street and St. Charles Road
Ordinance No.
16777 Council
Bill No. B 35-01
AN ORDINANCE
accepting the bid of C.L. Richardson Construction Company for construction of streets
improvements at the intersection of Keene Street and St. Charles Road; confirming the contract;
authorizing the City Manager to execute, obtain and record all documents necessary for the
improvement; providing for payment thereof; directing the contractor to give bond to the City;
providing for compliance with the prevailing wage law; and fixing the time when this ordinance
shall become effective.
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBIA, MISSOURI, AS
FOLLOWS:
SECTION 1. The bid of C.L. Richardson Construction Company
in the amount of $ 49,506.75
for the reconstruction of the intersection of Keene Street and St. Charles Road, all in accordance
with city of Columbia Street and Storm Sewer Specifications and Standards in the City of
Columbia, Boone County, Missouri , in accordance with the plans and specifications therefor, the
laws of the State of Missouri, and the Charter and Ordinances of the City, is the bid of the lowest
responsible bidder and is hereby accepted.
SECTION 2. The contract wherein the City Manager accepts
the bid of and lets the contract
for the improvement to the contractor is hereby confirmed.
SECTION 3. The City Manager is authorized and directed
to obtain, execute and have
recorded all contracts, licenses, easements, deeds and all other grants or conveyances necessary
for construction of the improvement.
SECTION 4. Payment for this improvement shall be made
from the capital improvement sales
tax funds and from such other funds as may be lawfully appropriated.
SECTION 5. The contractor shall give an approved
surety bond to the City in an amount not
less than the contract price, or a bond with two or more good and sufficient securities to be
approved by the City Manager, conditioned that the contractor will faithfully and completely
comply with all the terms and conditions of the contract, and that he will pay for all labor
employed and materials used in the work provided for in the contract, and will hold the City
harmless on account of any damage which may accrue to any person by reason of the negligence
of the contractor in constructing the work and against liens growing out of the labor performed or
materials furnished.
SECTION 6. The City shall cause to be inserted in the
contract a stipulation to the effect that
not less than the prevailing hourly rate of wages as determined by the Department of Labor and
Industrial Relations of Missouri shall be paid to all workers performing work under the contract.
The contractor's bond shall include such provisions as will guarantee the faithful performance
of
the prevailing hourly wage clause, as provided by the contract.
SECTION 7. This ordinance shall be in full force and effect
from and after its passage.
PASSED this 5th day of February, 2001.