Series 103 2002 ORDINANCES/RESOLUTIONS
Section 103-192; Ord. 17242; Change Order No. Six to Contract w/Phillips Grading and Construction, Inc. RE: Wetland Treatment Unit No. 4; Accepting and Approving the Work
Ordinance No.
17242 Council
Bill No. B 104-02
AN ORDINANCE
authorizing the City Manager to execute Change Order No. Six to the contract with Phillips
Grading and Construction, Inc. for construction of the Wetland Treatment Unit No. 4; setting
forth the nature and amount of change; accepting and approving the work; approving the report
of the Director of Public Works; and fixing the time when this ordinance shall become effective.
WHEREAS, construction of Wetland Treatment Unit No. 4 was authorized
by Ordinance No.
015881 passed on February 1, 1999; and
WHEREAS, this public improvement has been completed by Phillips
Grading and
Construction, Inc. pursuant to a contract confirmed by Ordinance No. 015963 passed on April
19, 1999.
NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF
COLUMBIA, MISSOURI, AS FOLLOWS:
SECTION 1. The City Manager is hereby authorized and directed
to execute Change Order
No. Six to the contract with Phillips Grading and Construction, Inc. for construction of Wetland
Treatment Unit No. 4.
SECTION 2. The nature and amount of the change is set
forth in Exhibit "A" attached hereto
and made a part hereof as fully as if set forth herein verbatim.
SECTION 3. The construction of Wetland Treatment Unit
No. 4 is hereby accepted and
approved.
SECTION 4. The report of the Director of the Public Works
Department, who was charged
with the responsibility of personally inspecting the work as it progressed to see that the work was
done in accordance with the estimate, plans, specifications and contract, the ordinance governing
the same and the Charter of the City is hereby approved and accepted.
SECTION 5. This ordinance shall be in full force and effect
from and after its passage.
PASSED this 1st day of April, 2002.