Section 103-418; Res. 138-02; Setting a Public Hearing RE: Construction of Water Mains Located in and Serving Stonecrest, Plat 4


Council Bill No.           R 138-02         
    
A RESOLUTION

declaring the necessity for the construction of water mains located in and serving Stonecrest, Plat 4; stating the nature of the improvement; estimating the extra cost for constructing 8-inch and 12-inch water mains rather than 6-inch and 8-inch water mains; providing that the improvement shall be made by Fred W. and Cheryl Overton; and setting a public hearing.

    WHEREAS, Fred W. and Cheryl Overton desires to install a 6-inch and an 8-inch water main to serve property abutting the proposed water main extension; and

    WHEREAS, the City for reasons of health, safety, public welfare, and future adequate service to areas other than Stonecrest, Plat 4, requires that an 8inch and a 12-inch water main be installed; and

    WHEREAS, plans and specifications for such installation have been prepared by the Director of the Water and Light Department.

    NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF COLUMBIA, MISSOURI, AS FOLLOWS:

    SECTION 1. The Council deems the construction of about 165 feet of 8inch and 720 feet of 12-inch water main pipes and accessory valves and fittings located in and serving Stonecrest, Plat 4, necessary to assure adequate future water supply for the health, safety and welfare of the citizens of the City.
    
    SECTION 2.  The nature and scope of the improvement shall consist of furnishing all labor, materials, transportation, insurance and all other items necessary for the complete construction of the water main described in Section 1.

    SECTION 3.  The estimated differential cost for an 8-inch water main (the cost of constructing an 8-inch water main which exceeds the cost for constructing a 6-inch water main) for this improvement is $ 6.50 per linear foot.  The estimated differential cost for a 12-inch water main (the cost of constructing a 12-inch water main which exceeds the cost of constructing an 8-inch water main) for this improvement is $ 11.11 per linear foot; and the cost of solid rock excavation, if necessary above that required to install an 8-inch water main, is $2.00 per linear foot.

    SECTION 4.  This improvement shall be made by Fred W. and Cheryl Overton.

    SECTION 5.  This resolution shall be published in a daily newspaper of general circulation in the City of Columbia for seven (7) consecutive insertions, and a public hearing in respect to this improvement will be held in the Council Chamber of the Daniel Boone Building, 701 E. Broadway, Columbia, Missouri, at 7:00 p.m., on August 19, 2002.

    ADOPTED this 5th day of August, 2002.