Section 106-390; Ord. 18597; Accepting and approving the work on the Grindstone Creek Outfall Sewer Extension project


Ordinance No.             18597                     Council Bill No.            B 237-05           


AN ORDINANCE

accepting and approving the work on the Grindstone Creek Outfall Sewer Extension project; approving the report of the Director of Public Works; and fixing the time when this ordinance shall become effective.

    WHEREAS, construction of the Grindstone Creek Outfall Sewer Extension was authorized by Ordinance No. 017637 passed on April 7, 2003; and

    WHEREAS, this public improvement has been completed by Sterling Excavation, Inc. pursuant to a contract confirmed by Ordinance No. 017710 passed on June 2, 2003.

    NOW, THEREFORE, BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBIA, MISSOURI, AS FOLLOWS:

    SECTION 1.    The construction of the Grindstone Creek Outfall Sewer Extension is hereby accepted and approved.

    SECTION 2.    The report of the Director of the Public Works Department, who was charged with the responsibility of personally inspecting the work as it progressed to see that the work was done in accordance with the estimate, plans, specifications and contract, the ordinance governing the same and the Charter of the City is hereby approved and accepted.

    SECTION 3.    This ordinance shall be in full force and effect from and after its passage.

    PASSED this 18th day of July, 2005.