Section 110-606; Res. 264-09; Declaring the necessity for the construction and extension of a 12-inch water main along Waco Road, from Brown Station to Arbor Pointe, serving The Villages at Arbor Pointe, Plat 3; setting a public hearing


Council Bill No. R 264-09

     A RESOLUTION

declaring the necessity for the construction and extension of a 12inch water main along Waco Road, from Brown Station Road to Arbor Pointe Parkway, serving The Villages at Arbor Pointe, Plat 3; stating the nature of the improvement; estimating the extra cost for constructing a 12-inch rather than an 8-inch water main; providing that the improvement shall be made by Premier LLC; providing that payment for the extra cost of constructing a larger water main shall be from water utility funds; and setting a public hearing.

    WHEREAS, Premier LLC desires to install an 8inch water main to serve property abutting the proposed water main extension; and

    WHEREAS, the City for reasons of health, safety, public welfare, and future adequate service to areas other than The Villages at Arbor Pointe, Plat 3, requires that a 12inch water main be installed; and

    WHEREAS, plans and specifications for such installation have been prepared by the Director of the Water and Light Department.

    NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF COLUMBIA, MISSOURI, AS FOLLOWS:

    SECTION 1.    The Council deems the construction of about 2,240 feet of 12inch water main pipes and accessory valves and fittings along Waco Road, from Brown Station Road to Arbor Pointe Parkway, serving The Villages at Arbor Pointe, Plat 3 necessary to assure adequate future water supply for the health, safety and welfare of the citizens of the City.

    SECTION 2.    The nature and scope of the improvement shall consist of furnishing all labor, materials, transportation, insurance and all other items necessary for the complete construction of the water main described in Section 1.

    SECTION 3.    The estimated differential cost (the cost of constructing a 12-inch water main which exceeds the cost of constructing an 8-inch water main) of this improvement is $9.82 per linear foot; and the estimated differential cost of solid rock excavation, if necessary, above that required to install an 8inch water main, is $2.00 per linear foot.

    SECTION 4.    This improvement shall be made by Premier LLC.

    SECTION 5.    Payment of differential costs, not to exceed the estimated amounts stated in Section 3, shall be made to Premier LLC from the Capital/Transmission and Distribution Mains Account upon satisfactory completion of the work and acceptance of the Engineer's Report by the City Council.

    SECTION 6.    A public hearing in respect to this improvement will be held in the Council Chamber of the Daniel Boone Building, 701 E. Broadway, Columbia, Missouri, at 7:00 p.m. on December 7, 2009.  The City Clerk shall cause notice of this hearing to be published in a newspaper published in the City.

    ADOPTED this 16th day of November, 2009.