| Funding Fiscal Year: | 2011 |
|---|---|
| Project Number: | C46071 |
| Project Budget: | $137,411* |
| Funding Source: | Donation** |
* Original budget - $90,000; increased budget after flooring bids were received.
**Funds appropriated from ARC donation account
(funds reserved from original ARC project development )
Project Description: Replace carpet tiles in upstairs cardio and strength training room with resilient athletic flooring.
Council Items: Click here.
Project Status: 03/31/11: Contractor working on site removing carpet tiles. A large portion of the carpet tiles will be recycled or saved for use in other areas of the ARC. On Monday, April 4, contractor will remove the saturated glue by using a grinding machine. Bring your headphones!
03/14/11: Materials arrived and located on site. Materials need to climatize to the ARC temperatures and humidity prior to being installed. Install to start end of March.
Major Vendors |
||||
|---|---|---|---|---|
| ** | Vendor |
Item |
Purchase Order# |
Amount |
| C | Combined Flooring | Install resilient flooring | 111067 | $130,920 |

ARC Cardio Area with Carpet Rermoved - Photo Taken 3-31-2011
Activity and Recreation Center (ARC)