Atkins Development - Youth Athletic Fields

Funding Fiscal Year(s): 2007 & 2008
Project Number: C00280
Project Budget : $1,435,355*
Funding Source:

$1,025,000 - Park Sales Tax
$76,005 - LWCF Grant
$103,995* - Boone County Government
$220,355 - Recreation User Fees
$10,000 - Diamond Council Donation

Year Completed: 2009
*Adjusted from original budget
Note: Road and parking lot paving funded by Annual Roads and Parking

Council Items: Click here.
Plans: Click here.
Project Description: The 80-acre property was donated by Tom Atkins to the City of Columbia and Boone County in 2002, with each having undivided one-half interest. Atkins donated the land with the intent that the land be developed for youth recreation. This project is the first phase of the construction of a new baseball field complex. Phase one includes the construction of two lighted baseball fields (400' field and 350' field), irrigation lake, and 140-car gravel parking lot. The two ball fields are part of a five-field tournament quality complex that will be completed as funding becomes available. Phase one also includes grading for the entire five field complex to prepare the site for future construction. Columbia Parks and Recreation Department will be responsible for the maintenance and programming of the complex when completed.

Project Notes: Due to the City Council's approval on June 19, 2006 of a Memorandum of Understanding with Columbia Professional Baseball for a proposed sports complex for a minor league baseball team (Columbia Diamonds, formerly the Mid-Missouri Mavericks) at American Legion Park, the City Council decided to move the $325,000 2005 Park Sales Tax ballot funds identified for American Legion Park improvements to the youth athletic fields at Atkins Park project. (See related Council items.) By the close of Fiscal Year 2009, Columbia Professional Baseball had not returned to the City to discuss an agreement for the use of American Legion Park. Therefore, in Fiscal Year 2010 a capital project was budgeted with Recreation User Fee funds for improvements to American Legion Park.

Project Status (in descending date order):

Major contract awards for this project are listed below. The remainder of the project will be accomplished with Parks and Recreation staff.

Major Vendors

Vendor Item Purchase Order # Contract Amount
A Civil Group Engineering services 071963 $20,000
A Civil Group Legal description for utility easement 081387 $825
Malicoat-Winslow Eng Electrical design 080730 $6,000
Wilcoxson Excavating Grading, fencing, top soil, walks, parking lot construction 072474 $546,998
Rost Superior Services Irrigation 072950 $80,128
Rost, Inc. Sod 080274 $43,519
Leroy's Sports Fields Infield red shale 080677, 082284 $44,168
Fry & Associates Player benches 072708 $3,595
LOW Masonry Block for utility bldg. 080977 $2,541
Rhad Baker Const Utility bldg. block wall const. 081148 $13,970
Reeder-Wright Ent. Utility bldg. roof const. 081454 $5,420
Brandy Elec, Inc. ball field lights 081663 $311,550
Nevco Scoreboards Scoreboards 081804 $15,371
Innovative Concepts Metal gates 082032 $3,132
Sellenriek Construction Boring services 081221 $2,319*
AB Creative Pre-fab shelter 091383 $13,450
Simon Steel Foul pole extensions 090987 $1,111
Fletcher-Reinhart Parking lot light poles 090732 $1,826
Most Dependable Fountains Water fountain w/jug filler & hose bib 090604 $2,690
Custom Fence Erosion control fencing 082489 $994
Water & Sewer Water pipe 090444 $1,380
Ag Coop Service Spread fertilizer 090439 $3,257
Frech Paving** Asphalt work** 082157 $21,796**
* Term and supply contract; amount is portion of contract for this project.
**More asphalt work for Atkins project was done under Annual Roads and Parking.

Initial site grading of two new baseball fields began July 2007.
Photo of site grading of Atkins Property 07/7/07
Site preparation continues 8/7/07.
Site grading at Atkins Property 8/7/07

Aerial view of infield irrigation system. Irrigation lines were installed and outfield topsoil distributed for both fields by 9/27/07.

aerial view of Atkins ball fields irrigation system under construction

Field #1 sod was installed 11/19/07. Irrigation system in operation.
Sod installation at Atkins Youth Athletic Complex
Fence pole installation - 4/7/08.
Photo of Atkins ball field fence pole installation
Fencing and sod near completion -6/25/08
photo of Atkins ball fields during construction
Installation of red shale warning track - 7/1/08
photo of skid loader placing red shale material
Preparation for bleacher pad - 7/1/08
photo of site preparation for concrete pour
Ball fields nearing completion - July 2008.
Photo of Atkins ball field nearing completion

Photo of ball fields lit at night.
Photo of light ball fields at Atkins Park

First games held on March 31, 2009.
Photo of ball game at Atkins Park
Atkins Park was dedicated on May 11, 2009. Click here for more information on the park dedication ceremony.
Photo of ribbon cutting at Atkins Park dedication

Thomas E. "Country" Atkins Jr. Memorial Park