| Funding Fiscal Year: | 2005 |
|---|---|
| Project Number: | C00218 |
Project Budget: |
$130,000 |
| Funding Source: | $100,000 - 1999 1/4 Cent Sales Tax $30,000 - Force Account Labor |
| Year Completed: | 2007 |
Council Items: Click here.
Plans: Click here.
Project Description: Construct new medium-sized reservable shelter with expanded patio and covered grill, 80-car lighted parking lot , and connecting sidewalks on southwest side of park. All work to be done with park force account labor, except for the earthwork and parking lot asphalt.
Project Notes: The garden plots were removed to make way for the new shelter and parking lot.
Project Status: Completed. Shelter named Ficklin Shelter.
Major Vendors |
|||
|---|---|---|---|
Vendor |
Item |
Purchase Order# |
Contract Amount |
| Richardson Excavation | Earth work | 061255 | $8,810* |
| Boone Quarry | Rock | 072093 | $19,249* |
| Central Concrete | Concrete | 052459 | $11,932* |
| Frech Paving | Asphalt parking lot | 072168 | $29,586** |
| Most Dependable Fountains | Water fountain w/jug filler | 072431 | $2,330** |
| Fry & Associates | Covered grill | 072429 | $511** |
* Term and supply contract
** Amount for this project only; part of larger contract
| 80-car parking lot to serve the south shelter. (Photo taken September 2007.) | ![]() |
| Completed medium-sized shelter with expanded patio and covered grill | ![]() |