Cosmo-Bethel New Shelter

Funding Fiscal Year: 2005
Project Number: C00218

Project Budget:

$130,000
Funding Source: $100,000 - 1999 1/4 Cent Sales Tax
$30,000 - Force Account Labor
Year Completed: 2007

Council Items: Click here.
Plans: Click here.
Project Description: Construct new medium-sized reservable shelter with expanded patio and covered grill, 80-car lighted parking lot , and connecting sidewalks on southwest side of park. All work to be done with park force account labor, except for the earthwork and parking lot asphalt.
Project Notes: The garden plots were removed to make way for the new shelter and parking lot.
Project Status: Completed. Shelter named Ficklin Shelter.

Major Vendors

Vendor
Item
Purchase Order#
Contract Amount
Richardson Excavation Earth work 061255 $8,810*
Boone Quarry Rock 072093 $19,249*
Central Concrete Concrete 052459 $11,932*
Frech Paving Asphalt parking lot 072168 $29,586**
Most Dependable Fountains Water fountain w/jug filler 072431 $2,330**
Fry & Associates Covered grill 072429 $511**

* Term and supply contract
** Amount for this project only; part of larger contract

 

80-car parking lot to serve the south shelter. (Photo taken September 2007.)
Photo of 80-car parking lot for new south shelter
Completed medium-sized shelter with expanded patio and covered grill
Photo of new south shelter at Cosmo-Bethel Park