| Funding Fiscal Year(s): | 2003 & 2004 |
|---|---|
| Project Number: | C46065 |
| Project Budget : | $250,000 |
| Funding Source: | 99 1/4 Cent Sales Tax |
| Year Completed: | 2005 |
Project Status: Completed.
Park Map:
Click here.
Project Description: Construction of two new lighted softball fields with 200' fences and 45 car parking lot as an addition to the Antimi ball field Complex in Cosmo Park. Major contract awards for this project are listed below. The remainder of the project was accomplished with Parks and Rec crews.
Major Vendors |
|||
|---|---|---|---|
| Vendor | Item | Purchase Order # | Contract Amount |
| Roy Richardson Excavating | Grading for fields | 012677 | Term & Supply |
| La Cross Lumber | Fencing materials | 041699 | $34,917 |
| Christenson Construction | Asphalt parking lot | 042810 | $15,615 |
| Musco Sports Lighting | ball field lights & installation | 041753 | $73,335 |
| Fry & Associates | Bleachers & player benches | 052096 | $6,047 |
| Parks and Rec crew working on ball field construction. | ![]() |
| Parks and Rec crew installing ball field fence. | ![]() |
| New Gold Field first year in operation. | ![]() |
| Funding Fiscal Year: | 2005 |
|---|---|
| Project Number: | C46065 |
| Project Budget : | $225,000 in CIP $40,113 in fund transfers |
| Funding Source: | $225,000 - RSR $40,113 - Park Sales Tax |
| Year Completed: | 2006 |
Project Status: Completed.
Project Description: Demolish old concession/restroom building and construct new two-story concession/restroom building. Project also included electrical upgrades for the building, ball field lighting, and scoreboards, installed by Parks and Rec crews.
Major Vendors |
|||
|---|---|---|---|
| Vendor | Item | Purchase Order # | Contract Amount |
| Columbia Assoc Architects | Architectural services | 052432 | $18,061 |
| Crawford Construction | Building construction | 053501 | $245,770 |
| Parks and Rec staff demolishing old Antimi concession building. | ![]() |
| Newly constructed two-story Antimi concession building. | ![]() |
| Funding Fiscal Year: | 2007 |
|---|---|
| Project Number: | C46065 |
| Project Budget : | $200,000 |
| Funding Source: | RSR |
| Project Completed: | 2008 |
Project Description: Construction of concrete walkways and patio for complex. Purchase new bleachers and construct shade structures for bleachers. Install irrigation on Black and Gold Fields with force account labor.
Project Status: Construction of concrete walkways and patios is completed. New bleachers have been purchased, assembled, and are in use. Staff constructed concrete bases, installed shade structures and stained the concrete. Staff has completed irrigation installation on the Black and Gold Fields.
Major Vendors |
|||
|---|---|---|---|
| Vendor | Item | Purchase Order # | Contract Amount |
| Tom Adair Construction | Concrete work | 071103 | $45,100 |
| BSN Sports | Bleachers | 070846 | $20,143 |
| Riggs Recreation | Shade structures | 071347 | $63,972 |
| Portalite Products | Portable pitching mound | 072198 | $3,130 |
| Construction of concrete walks and patios replaced gravel areas. | ![]() |
| The Antimi Complex was re-dedicated on May 15, 2007. | ![]() |