| Fiscal Funding Year(s): |
2006 & 2007 |
| Project Budget: |
$750,000 |
| Funding Source: |
$650,000 Park Sales Tax; $100,000 USTA Grant |
| Year Completed: |
2007 |
Council Items: Click here.
Plans: Click here.
Project Description: Demolish and rebuild tennis complexes at Fairview Park and Cosmo Park with California corner style fencing. The complex at Cosmo Park was completely redesigned from one row of eight courts to two sections side by side of four courts each. New lighting was installed at the Cosmo courts.
Project Status: Completed.
Major Vendors
|
| Vendor |
Item |
Purchase Order # |
Contract Amount |
| APAC, Inc. |
Tennis Court Construction |
062879 |
$601,405 |
| Barton Electric |
Lighting & Installation |
071323 |
$89,000 |
Fairview Tennis Complex
| Condition of the courts before renovation. The cracks could no longer be repaired with re-coating. |
 |
| Courts were completely demolished and rebuilt. |
 |
| Court construction. |
 |
| Completed four-court Fairview Tennis Complex. |
 |
Cosmo Tennis Court Complex
| Condition of Cosmo Tennis Courts before renovation |
 |
| Layout of tennis courts before renovation |
 |
| Courts were completely demolished and rebuilt. |
 |
| Completed lighted tennis complex at Cosmo Park with two sections side by side of four courts each. |
 |
Tennis Court Dedication
| Several gathered at Cosmo Park on a stormy evening to celebrate the dedication of the new tennis complexes. |
 |
| Ribbon cutting at the dedication of the Thomas A. Rapp Tennis Courts at Cosmo Park on May 15, 2007. |
 |
Tennis Dedication Program
Cosmo Park
Fairview Park
Capital Improvement Program