Parks & Recreation
Creating Community through People, Parks and Programs
| Funding Fiscal Year : |
2008 |
| Project Number: |
C00344 |
| Project Budget: |
$240,000* |
| Funding Source: |
Park Sales Tax |
| Project Completed: |
2008 |
* Revised budget; original CIP budget - $175,000
Council Items: Click here.
Map of Restroom Locations: Click here.
Project Description:
Replace the two old restroom facilities that serve
Burford/Dexheimer and Nickell/Lamb Shelters on the south side of Cosmo Park.
Public Meeting : An informal Open House/Public Meeting concerning the replacement of the Nickell/Lamb and Burford/Dexheimer Restrooms in Cosmo Park was held Thursday, October 18, between 6:00 p.m. and 7:00 p.m. at ARC (Activity and Recreation Center), 1701 West Ash Street, Meeting Room A. Click here for press release. Attendees and park user groups expressed support for this project.
Project Status:
- 11/10/08 - Punch list and seeding/strawing completed. Project complete.
- 10/1/08 - Restrooms completed, except for punch list and landscaping.
- 9/1/08 - Trim work, soffit, interior plywood, painting, electrical and rough plumbing completed on both restrooms. Metal roof also completed on Burford/Descheimer restroom.
- 8/1/08 - Block walls, stone facade, and roof framing complete for Burford/Dexheimer restroom. Roof framing, utility rough in , stone facade, and metal roof complete for Nickell/Lamb restroom.
- 7/7/08 - Footings completed for both restrooms. Utilities have been roughed in, slab poured, and block walls completed for Nickell/Lamb restroom.
- 5/26/08 - Demo of the two restrooms completed. Contractor has begun pouring footings.
- 4/16/08 - Contractor obtaining necessary permits. Demolition work is expected to begin in April.
- 3/18/08 - Contract awarded.
- 2/13/08 - Bid for restroom demolition and construction closed.
- 11/20/07 -The project was introduced at the November 5, 2007 City Council meeting and a public hearing was held at the Council's November 19, 2007meeting. Council approved and authorized project.
- 11/21/07 - Bid specifications being developed by park planners.
- 10/16/07 - Public meeting for interested parties was held on October 16, 2007 at the ARC.
Major Vendors |
Vendor |
Item |
Purchase Order# |
Contract Amount |
| GBH Builders, Inc. |
Restroom demo & construction |
081675 |
$229,418* |
*Amount for this project only; part of larger contract.
| Old restroom facility to be replaced that serves Burford and Dexheimer Shelters. |
|
| New Burford-Dexheimer restroom. |
|
| Old restroom facility to be replaced that serves Nickell and Lamb Shelters. |
 |
| New Nickell-Lamb restroom. |
|
Cosmo Park
Capital Improvement Program