| Funding Fiscal Year: | 2009 |
|---|---|
| Project Number: | C00416 |
| Project Budget: | $55,000 |
| Funding Source: | Park Sales Tax |
| Year Completed: | 2010 |
Council Items: Click here.
Plans: Click here.
Project Description:
Removal of old fencing, construction of new bleacher pads, dugout painting, turf renovation, and installation of new fencing and gates.
Interested Parties Meeting: Meeting was held at 6:00pm, Monday, November 24, 2008 at the Armory Sports and Recreation Center, 701 E. Ash Street.
Project Notes: A public hearing was held and the ordinance to proceed with the construction of the project was approved at the January 20, 2009 Council Meeting.
Project Status: Project completed. Ballfields were placed in service for scheduled games June 21, 2010.
Major Vendors |
||||
|---|---|---|---|---|
| ** | Vendor | Item | Purchase Order # | Contract Amount |
| C | Designer Fence | Back field fencing and installation Construction of concrete mowing curb |
102108 | $3,881 |
| C | Tom Adair Const | Concrete bleacher pad construction | 091543 | $2,648* |
| M | Red Weir Athletics | Portable mounds, backstop padding, and bleachers | 092019 | $4,214 |
| C | James Fencing | Fencing and Installation | 091752 | $6,600 |
| M | Ri-Mor Topsoil | Topsoil | 051670 | $4,640* |
| C | Richardson Excavation | Grading | 061255 | $4,213* |
| M | Supreme Turf | Turface | 071685 | $1,776* |
* Amount for this project only; part of a term and supply contract
** C = contract work; M = materials only
| New concrete bleacher pads. | ![]() |
New gates and fencing. |
![]() |
| Newly painted dugout. (Photo taken 7/7/09.) |
![]() |
| Park staff seeding ballfield. (Photo taken 3/8/10.) |
![]() |
Completed Douglass ballfield. |
![]() |