| Funding Fiscal Year: | 2010 |
|---|---|
| Project Number: | C00445 |
| Project Budget: | $130,000 |
| Funding Source: | Park Sales Tax |
Project Description: New development on the northeast side of the park and improvements to the west side of the park.
Project Manager: Mike Snyder, Sr. Park Planner, 573-874-7204, MTS@GoColumbiaMo.com
Council Items: Click here.
Proposed Plan - Revised (12/31/2009): Click here.
Former proposed plan presented at 12/15/09 I.P. Meeting: Click here.
Interested Parties Meeting(s): An interested parties meeting was held from 6-7pm on December 15, 2009 at the Lake of the Woods Visitors Center with 12 people in attendance. A second interested parties meeting was held from 6-7pm on Thursday, January 28, 2010 with 15 people in attendance.
Project Notes: Park planners devised a proposed plan for the park improvements. An interested parties meeting for the public to view the proposed plan and provide input is was held on December 15, 2009 at the Lake of the Woods Visitors Center. Park revised the proposed plan based on public input. A park planning meeting was held on January 28, 2010 for citizens to review the revised proposed plan and offer comments. A public hearing was held and the project received approval to proceed at the March 15, 2010 Council Meeting.
Project Status: East playground and west playgrounds have been installed and construction of cul-de-sac and sidewalk on the east side of the park is completed. Installation of the dog park fencing is underway.
Major Vendors |
||||
|---|---|---|---|---|
| ** | Vendor |
Item |
Purchase Order# |
Contract Amount |
| M | Natural Structures | Single table shelters | 102969 | $5,808 |
| C | Stockman Construction | Cul-de-sac construction | 103491 | $26,337 |
| C | All Inclusive Rec | Playground (west) & installation | 103348 | $23,660 |
| C | Fry & Associates | Playground (east) & installation | 103350 | $20,800 |
| M | LaCrosse Lumber | Estate fencing | 103037 | $8,142 |
| C | Richardson Excavation | Earthwork | 061255 | $2,525* |
| M | BJ Services | Playground mulch | 081656 | $3,384* |
*Amount for this project only; part of term and supply contract.
** C = contract work; M = materials only