Columbia Parks and Recreation
Creating Community through People, Parks and Programs
Browse GoColumbiaMo.com Skip top Navigation. Translate this page


Funds are budgeted annually, when available, in the Capital Improvement Program for improvements to park roads and parking.This provides a funding source to upgrade existing park roads and parking lots as they deteriorate. Work often consists of asphalt overlays or sealing. New parking lots are sometimes packaged with the maintenance projects to obtain a better bid price. These improvements help maintain the quality and safety standards that have been established for park roads and parking areas. Funds not used in one fiscal year roll over to the next fiscal year.
| Funding Fiscal Year: | 2007 |
|---|---|
| Project Number: | C00242 |
| Project Budget: | $100,000 |
| Funding Source: | Park Sales Tax |
| Year Completed: | 2007 |
Project Description: Frech Paving Company was awarded the bid in the amount of $109,006.33, PO #072168, for the 2007 park roads and parking projects listed below.
Project Status: Completed
| Project Cost | Location | Project Description |
|---|---|---|
$29,586 |
Cosmo-Bethel South Shelter Lot | Asphalt new lot |
$39,041 |
Harris Shelter, Cosmo Park | Asphalt new lot |
$6,912 |
Tennis Parking Lot, Cosmo Park | Ashpalt overlay |
$17,091.33 |
ARC Parking Lot | Asphalt repair |
$1,565.50 |
Antimi Gold Lot, Cosmo Park | Asphalt seal coat |
$6,241.50 |
Douglass Park Lot | Asphalt overlay |
$7,319 |
Flat Branch Park, Elm Street | Asphalt new lot |
| Funding Fiscal Year: | 2008 |
|---|---|
| Project Number: | C00242 |
| Project Budget: | $160,000 |
| Funding Source: | Park Sales Tax |
| Year Completed: | 2008 |
Project Description:2008 projects are listed below. Other alternate projects may be added, as funding allows.
Project Status: Frech Paving Company was awarded the asphalt bid in the amount of $82,440, PO#08157. Atkins Park entry road completed. The parking lot at Atkins Park has been re-graded to prep for asphalt work. See also Garth Nature Area Parking Lot Expansion.
| Project Cost | Location | Project Description |
|---|---|---|
$82,440 |
Atkins Baseball Fields | Asphalt pave entry road and parking lot |
| $20,000 | (See) Garth Nature Area | Grade and rock expanded parking area |
| Funding Fiscal Year: | 2009 |
|---|---|
| Project Number: | C00242 |
| Project Budget: | $160,000 |
| Funding Source: | Park Sales Tax |
| Year Completed: | 2010 |
Project Description: Park road and parking lot improvements in Columbia's park system. List of projects is determined annually.
Project Notes: Phase 2 of the Garth Nature Area parking lot expansion was funded out of 2009 Annual Park Roads and Parking, with a budget of $28,290. The remaining road and parking lot projects were awarded to Frech Paving company in the amount of $79,824.71, PO#091704. The second round of bids for asphalt work was also awarded to Frech Paving Company in the amount of $49,657, PO#092542.
Project Status: All 2009 road and parking lot improvement projects are completed.
| PO# 091704 - Frech Paving Company | |||
|---|---|---|---|
| Project Cost | Location | Project Description | Status |
$21,000 |
CCRA Entrance | Asphalt overlay | Completed |
$3,695 |
PMC Parking Lot Expansion | Asphalt lot (new) | Completed |
$11,084 |
CCRA Antimi T-ball Lot | Asphalt lot (new) | Completed |
$6,283 |
Valleyview Basketball | Demo and new asphalt | Completed |
$2,239 |
CCRA Circle | Seal asphalt | Completed |
$2,744 |
CCRA Schwabe | Seal asphalt | Completed |
$3,036 |
Grindstone parking lot | Seal asphalt | Completed |
| $11,467 | PMC existing parking lot | Chipseal overlay | Completed |
| $9,761 | PMC front drive | Asphalt overlay | Completed |
| $8,580 | LOW Entry Drive PMC CCRA Antimi T-ball Lot Rock Quarry Park Drive |
Additional wedge and asphalt repair | Completed Completed Completed Completed |
| PO# 092542 - Frech Paving Company | |||
|---|---|---|---|
| Project Cost | Location | Project Description | Status |
$16,154 |
Forum Nature Area parking lot | Overlay and seal | Completed |
$8,745 |
American Legion drive | Overlay | Completed |
$18,293 |
Capen Park drive and lot | Surface prep and new asphalt | Completed |
$6,465 |
Albert-Oakland Park asphalt walks | Repair | Completed |
| $3,450 | Albert-Oakland Park west section | Repair | Completed |
| * | |||
| PO# 092555 -Stockman Construction | |||
| Project Cost | Location | Project Description | Status |
| $24,940 | Smiley Lane Park cul-de-sac | Construct concrete cul-de-sac | Completed |
| Funding Fiscal Year: | 2010 |
|---|---|
| Project Number: | C00242 |
| Project Budget: | $160,000 |
| Funding Source: | Park Sales Tax |
| Year Completed: | 2010 |
Project Description: Park road and parking lot improvements in Columbia's park system. List of projects is determined annually. Projects chosen for FY 2010 funding are listed below.
Project Status:
Completed.
| PO# 102874 - Christensen Construction Company - $106,622 | |||
|---|---|---|---|
| Project Cost | Location | Project Description |
Status |
$8,611 |
Atkins Park, entry road | Repair | Completed |
| $1,562 | Stephens Lake Park, Broadway upper drive | Seal | Completed |
$3,370 |
Stephens Lake Park, upper lot | Seal | Completed |
$990 |
Stephens Lake Park, east lot | Seal | Completed |
$3,782 |
Stephens Lake Park, east lot drive | Seal | Completed |
| $4,502 | Stephens Lake Park, Old 63 parking lot | Seal | Completed |
| $2,885 | Stephens Lake Park, Riechmann parking lot | Seal | Completed |
| $2,100 | Albert-Oakland Park, Edris Drive lot | Seal | Completed |
| $1,700 | Rock Quarry Park, entry drive | Seal | Completed |
| $2,160 | Rock Quarry Park, parking lot | Seal | Completed |
$42,199 |
CCRA, north road | Overlay | Completed |
| $2,300 | CCRA, Parkside Drive/circle entry | Seal | Completed |
| $1,500 | CCRA, Antimi Black Field parking lot | Seal | Completed |
| $1,500 | CCRA, RC track parking lot | Seal | Completed |
| $5,100 | CCRA, T-ball road | Seal | Completed |
$18,703 |
L.A. Nickell Golf Course, cart shed parking lot | Overlay | Completed |
| $1,485 | L.A. Nickell Golf Course, cart shed parking lot | Repair | Completed |
| $2,172.50 | L.A. Nickell Golf Course, entry | Repair & overlay | Completed |
| PO# 103744 - Tom Adair Construction | |||
| Project Cost | Location | Project Description |
Status |
| $36,133 | ARC, parking lot, phase 1 | Repair and change over from asphalt to concrete | Completed |
| Funding Fiscal Year: | 2011 |
|---|---|
| Project Number: | C00242 |
| Project Budget: | $160,000 |
| Funding Source: | Park Sales Tax |
| Year Completed: | 2011 |
Project Description: Park road and parking lot improvements in Columbia's park system. List of projects is determined annually.
Project Manager: Toney Lowery, Sr. Park Planner, 573-874-7537, AJLowery@GoColumbiaMo.com
Project Status: First round of bids was to complete the repair of phases 2 and 3 of the ARC parking lot, converting the lot from asphalt to concrete. Phases 1-3 of the ARC parking lot project are completed, which is about 20% of the total parking lot. The rest of the 2011 asphalt project bids were awarded in September 2011 and will be scheduled in the fall of 2011, weather permitting.
| PO# 110339 - Tom Adair Construction | |||
|---|---|---|---|
| Project Cost | Location | Project Description |
Status |
| $59,552.50 | ARC, parking lot, phases 2 & 3 | Repair and change over from asphalt to concrete | Completed |
| PO# 120545* - Frech Paving Company | |||
| Project Cost | Location | Project Description |
Status |
| $18,000 | Atkins Park Entrance Road | Asphalt repair | Completed |
| $34,500 | Atkins Park Entrance Road | Asphalt overlay | Completed |
| $10,000 | Atkins Park Entrance Road | Wedge | Completed |
| $1,500 | Atkins Park Entrance Road | Speed bumps | Completed |
| $2,500 | Old 63 Roadside Park Lot | Remove old asphalt (see plan) | Completed |
| $13,000 | Old 63 Roadside Park Lot | New asphalt (see plan) | Completed |
| * Items listed for this PO are for the portion charged to Annual Roads and Parking only | |||
| Funding Fiscal Year: | 2012 |
|---|---|
| Project Number: | C00242 |
| Project Budget: | $150,000 |
| Funding Source: | Park Sales Tax |
| Year Completed: | 2012 |
Project Description: Park road and parking lot improvements in Columbia's park system. List of projects is determined annually. Priority: Repair Twin Lakes Recreation Area road, put electric underground, and make connections to County House Trail. As funds allow - repair and overlay interior asphalt at Rainbow Softball Center.
Project Manager: Toney Lowery, Sr. Park Planner, 573-874-7537, AJLowery@GoColumbiaMo.com
Project Status: Work at Twin Lakes completed, including repair to Twin Lakes entry road, putting electric underground, and making connections to County House Trail. Ashpalt work at Rainbow Softball Center is nearing completion.
| PO# 120879 - Christensen Construction | |||
|---|---|---|---|
| Project Cost | Location | Project Description |
Status |
| $55,215 | Twin Lakes Recreation Area - entry road | Repair and overlay | Completed |
Major Vendors - Work at Twin Lakes Recreation Area |
|||
|---|---|---|---|
Amount |
Vendor |
Description |
Purchase Order# |
| $28,441 | Boone Quarries | Rock | 103856 |
| $3,698 | Ri-Mor Topsoil | Topsoil | 102337 |
| $11,839 | Richardson Excavation | Earthwork | 111103 |
| $10,556 | Tom Adair Construction | Concrete work | 91543 |
| $2,888 | Water & Sewer | Pipe | 102884 |
| PO# 122021 - Christensen Construction | |||
|---|---|---|---|
| Project Cost | Location | Project Description |
Status |
| $49,170 | Rainbow Softball Center - asphalt within complex (entranceway and accesses to four fields) | Repair and overlay | Completed |
| Funding Fiscal Year: | 2013 |
|---|---|
| Project Number: | C00242 |
| Project Budget: | $150,000 |
| Funding Source: | Park Sales Tax |
Project Description: Park road and parking lot improvements in Columbia's park system. List of projects is determined annually.
Project Manager: Toney Lowery, Sr. Park Planner, 573-874-7537, AJLowery@GoColumbiaMo.com
Project Status: Planning stage.
Follow Us: