In Fiscal Year 2007, $85,000 was budgeted in the Capital Improvement Program for major park maintenance and small renovation projects. Projects are proposed annually by the Parks and Recreation Department and submitted for approval through the City Council. Any unused fund balance is reserved for potential grant matches or other unanticipated projects that may require mid-year funding. The projects below were chosen as 2007 annual park improvement projects.
Hickman Pool Sign
Council Items: Click here |
![]() |
| Funding Fiscal Year: | 2007 |
|---|---|
| Project Number: | C00295 |
| Project Budget: | $42,000 |
| Funding Source: | Annual Parks - Park Sales Tax |
| Year Completed: | 2009 |
Council Items: Click here
Plans: Click here
Project Description: Construct a 12-foot-wide gravel walkway down the center of the Historic Village connecting to an existing walkway at the Nifong Animal Barn; move the lake dam south and increase the lake size and depth; and install security lighting at the historical village.
Project Status:
Major Vendors |
|||
|---|---|---|---|
| Vendor | Item | Purchase Order # | Contract Amount |
| Richardson Excavation | Earthwork | 061255 | $33,385* |
| Water and Sewer | Pipe | 090724 | $1,804 |
| Boone Quarries | Rock | 062414, 072093, 082967 | $10,514 |
| Ahrens Steel | Gates | 081008 | $1,396 |
| Bank of America - ASP | Straw Mats & Wattles | (FPO's) | $1,943 |
| Completed Historic Village walkway. | ![]() |
| Work in progress on Nifong Lake. | ![]() |
| Nifong Lake partially full. (Photo taken December 2008.) |
![]() |
| Park staff doing grading work. (Photo taken March 2009.) |
![]() |
| Funding Fiscal Year: | 2007 |
|---|---|
| Project Number: | C00296 |
| Project Budget: | $12,215* |
| Funding Source: | Annual Parks - Park Sales Tax |
| Year Completed: | 2008 |
Council Items: Click here
Plans: Click here.
Project Description:
Replace specific gravel sections of the Valleyview Park trail with concrete to reduce maintenance costs resulting from areas that wash out following heavy rains.
Project Status: Completed.
Major Vendors |
|||
|---|---|---|---|
| Vendor | Item | Purchase Order # | Contract Amount |
| Adair Construction | Concrete work | 081288 | $8,685* |
| Water & Sewer | 30" HDPE Culvert Pipe | F77248 | $289 |
| Water & Sewer | 36" HDPE Culvert Pipe | F74679 | $862 |
| Photo of two culverts installed for Valleview Trail. | ![]() |
| 410 feet of the northeast portion of the gravel trail was replaced with concrete. Staff seeded and placed strawed along the new concrete. | ![]() |