2007 Annual Park Improvement Projects

In Fiscal Year 2007, $85,000 was budgeted in the Capital Improvement Program for major park maintenance and small renovation projects. Projects are proposed annually by the Parks and Recreation Department and submitted for approval through the City Council. Any unused fund balance is reserved for potential grant matches or other unanticipated projects that may require mid-year funding. The projects below were chosen as 2007 annual park improvement projects.


Hickman Pool Sign

Funding Fiscal Year: 2007
Project Number: C00297
Project Budget: $2,500
Funding Source: Annual Parks - Park Sales Tax
Year Completed: 2007

Council Items: Click here
Project Description: Replaced 20-year-old wooden Hickman Pool sign with new aluminum sign installed by park staff.
Project Status: Completed.

Hickman High School

Photo of Hickman Pool sign

Nifong Park Improvements

Funding Fiscal Year: 2007
Project Number: C00295
Project Budget: $42,000
Funding Source: Annual Parks - Park Sales Tax
Year Completed: 2009

Council Items: Click here
Plans: Click here
Project Description: Construct a 12-foot-wide gravel walkway down the center of the Historic Village connecting to an existing walkway at the Nifong Animal Barn; move the lake dam south and increase the lake size and depth; and install security lighting at the historical village.

Project Status:

Major Vendors

Vendor Item Purchase Order # Contract Amount
Richardson Excavation Earthwork 061255 $33,385*
Water and Sewer Pipe 090724 $1,804
Boone Quarries Rock 062414, 072093, 082967 $10,514
Ahrens Steel Gates 081008 $1,396
Bank of America - ASP Straw Mats & Wattles (FPO's) $1,943
* Amount is for this project only - part of a term and supply contract.

 

Completed Historic Village walkway.
Photo of Historic Village walkway
Work in progress on Nifong Lake.
Photo of Nifong Lake work
Nifong Lake partially full.
(Photo taken December 2008.)
Photo of Nifong Lake partially full
Park staff doing grading work.
(Photo taken March 2009.)
Photo of Park staff doing grading work at Nifong Park

Nifong Park


Valleyview Park Trail Improvements

Funding Fiscal Year: 2007
Project Number: C00296
Project Budget: $12,215*
Funding Source: Annual Parks - Park Sales Tax
Year Completed: 2008
*Revised budget

Council Items: Click here
Plans:
Click here.
Project Description: Replace specific gravel sections of the Valleyview Park trail with concrete to reduce maintenance costs resulting from areas that wash out following heavy rains.
Project Status: Completed.

Major Vendors

Vendor Item Purchase Order # Contract Amount
Adair Construction Concrete work 081288 $8,685*
Water & Sewer 30" HDPE Culvert Pipe F77248 $289
Water & Sewer 36" HDPE Culvert Pipe F74679 $862
*Amount for this project only - part of term and supply contract

 

Photo of two culverts installed for Valleview Trail.
Photo of culverts installed at Valleyview Trail
410 feet of the northeast portion of the gravel trail was replaced with concrete. Staff seeded and placed strawed along the new concrete.
Photo of trail portion that was replaced with concrete at Valleyview Park

 

Valleyview Park


Cosmo-Bethel Tennis Court Resurfacing


Capital Improvement Program

 
 
contact us