Scott's Branch Trail Development

Phase I - Bonnie View Park to Scott Blvd/MKT

Funding Fiscal Year(s): 2009 - $100,000
2010 - $680,000
Project Number: C00422
Project Budget: $780,000
Funding Source(s): Park Sales Tax

Phase II - Scott Blvd. to Gillespie Bridge Road

Funding Fiscal Year(s): 2011 - $200,000
Project Number: C00461
Project Budget: $200,000
Funding Source(s): Park Sales Tax

Note: As a result of proposed revisions to trail route, costs are expected to be less than original proposed funding amount. The $590,000 appropriation for Phase II originally proposed in 2012 will be deferred or moved to another trail project.

Project Description (both phases): Acquire trail easements and construct needed trail portions from Bonnie View Park to Scott Blvd, making a connection to the MKT Trail. Trail route will also utilize existing and and planned sidewalks/pedways. Plans include improvements to the intersection of Gillespie Bridge and Chapel HIll Roads to facilitate a connection to the future Perche Creek Trail.

Items to be funded by both phases include:

Project Manager: Steve Saitta, Superintendent of Planning and Development, 573-874-7203, SMS@GoColumbiaMo.com

Council Items: Council Agenda Items

Related Item: Bonnie View Nature Area Development

Proposed Plans:
Scotts Branch Trail - Entire Route

Link to Scotts Branch Trail Plan

Trail Route Descriptions:

Project Status: Trail easements south of Dublin Avenue have been acquired. After collecting public input for the Bonnie View/Fairview Park master plan, park planners have completed a revised proposed trail route for Scotts Branch Trail. A public hearing on the project was held at the March 21, 2011 Council Meeting. The Council decided to refer the project to the Bicycle/Pedestrian Commission and requested a report from the Parks and Recreation Department on an alternate route option. The requested report appears on the April 4, 2011 Council Agenda.

Major Vendors

Vendor Item Purchase Order # Contract Amount
Allstate Consultants Trail survey 090673 $4,500*

* Amount is portion of contract for this project; part of larger contract.