| Funding Fiscal Year: | 2006 - $570,000 2007 - $210,000 2010 - $60,000 (fund transfer) |
|---|---|
| Project Number: | C00245* |
| Project Budget: | $840,000** |
| Funding Source(s): | $468,000 - STP Enhancement Grant $228,000 - 1999 1/4 Cent Sales Tax (PYA) $144,000 - Park Sales Tax |
PYA = Prior Year Appropriation
* Note: Project # C00281 for Phase II has been closed and its budget and expenses have been combined with C00245.
** Revised budget - includes $60,000 fund transfer (original budget - $780,000)
Project Description: October 1, 2009: Descriptions of Phase I & II have been revised for funding and bidding purposes, as follows:
Project Manager: Steve Saitta, Superintendent of Planning and Development, 573-874-7203, SMS@GoColumbiaMo.com
Council Items: Click here.
Plans:Click here.
Interested Parties Meeting: Held January 29, 2008.
Project Notes: City received approval from MoDot to combine Grindstone to Stephens Phase I and Phase II STP Grant projects. HNTB Corporation has been contracted as the engineering firm for both phases. City received approval from MoDot to use Non-Motorized Transportation Pilot Program funds to finance Phase II (updated description above). Supplemental agreement #2 with consultant to complete a feasibility study for a low water crossing for Hinkson Creek and the crossing under the Hinkson Creek Bridge on Old 63 has been executed, and consultants have begun feasibility design work. Public hearing for project was held at the February 2, 2009 Council meeting. Air space agreement with MoDOT approved at the April 6, 2009 Council Meeting. A supplemental agreement with MoDOT adjusting the project time line was approved at the February 15, 2010 Council Meeting.
Major Vendors |
|||
|---|---|---|---|
| Vendor | Item | Purchase Order # | Contract Amount |
| Allstate Consultants | Engineering services | 071949 | $3,891 |
| HNTB Corp | Engineering services | 070831 | $78,090 |
| JC Industries | Trail construction | 103553 | $747,009 |
| Funding Fiscal Year: | 2007 - $40,000 2008 - $400,000 |
|---|---|
| Project Number: | C00284 |
| Project Budget: | $440,000 |
| Funding Source(s): | Park Sales Tax |
Project Description: 1.1 mile trail extension of Hinkson Creek Trail connecting to Rockhill Park & Bluff Dale Drive.
Map:
Click here.
Interested Parties Meeting: Held January 29, 2008.
Project Status: This project was not approved by City Council. Funds have been reallocated. See related Council item.